CAMCE Signing Commercial Contract of O/T 400kV Power Transmission Project in Zimbabwe

By: From: Posted: 2017-12-21 13:34:00 FontSize: BIG MIDDLE SMALL

    CAMCE signs Commercial Contract of O/T 400kV Power Transmission Project in Zimbabwe with Zimbabwe Electricity Transmission & Distribution Company on the morning of 15th, December 2017. Vice President Hu Wei of CAMCE and President Julian Chinembiri of Zimbabwe Electricity Transmission & Distribution Company sign the contract.

    The contract amount of this project stands at USD 145,653,300. The project locates at Manicaland and Masvingo of Zimbabwe, and the project scope includes building 400kV transmission line of 300 kilometers and upgrading of 3 substations with completion period of 30 months.

 

 